Archaeology before you build:
the law, the sources, the LiDAR.
Before construction in Poland, archaeology turns up in three places: the desk-based search before a purchase or a design, the environmental impact assessment report, and the decisions of the voivodeship conservator of monuments. This guide sets out the provisions behind each, with article numbers and links to the official texts.
The second half is practical: how to add a review of airborne laser scanning (LiDAR) to the desk stage and what to expect from it. It points to places worth checking. It does not replace any research the law requires.
- Updated
- 11 October 2026
- Reading time
- 11 min
On this page09
- 01When the law requires archaeological work
- 02Who pays
- 03Forms of protection: register, records, local plan
- 04Monuments in the environmental impact report
- 05When something turns up during works
- 06Sources for a desk-based search
- 07Why the register is not enough
- 08What to check at each stage
- 09Adding LiDAR screening to the desk stage
When the law requires archaeological work
The core provision is art. 31 of the Act on the protection and care of monuments (ustawa o ochronie zabytków i opiece nad zabytkami). Under art. 31(1a), a person or organisation that intends to carry out building works at an immovable monument, or earthworks or a change in how land is used where archaeological monuments are located, which may transform or destroy an archaeological monument, must cover the cost of archaeological research and its documentation, if that research is necessary to protect the monuments.
Art. 31(1a)(1) covers building works at an immovable monument entered in the register, protected under the provisions of a local zoning plan, or included in the voivodeship conservator’s records. Art. 31(1a)(2) covers earthworks on land where archaeological monuments are located. The scope and type of the necessary research are set by the voivodeship conservator of monuments by way of an administrative decision, and only to the extent that the works will destroy or damage an archaeological monument (art. 31(2)). After the research, a copy of the documentation goes to the conservator free of charge (art. 31(3)).
Every archaeological investigation needs a permit from the voivodeship conservator (art. 36(1)(5)). It must be led by a person with a master’s degree in archaeology and at least 12 months of participation in archaeological research (art. 37e). The Act defines archaeological research as activities aimed at discovering, identifying, documenting and securing an archaeological monument (art. 3(11)).
The earlier wording of art. 31(1), which made the developer pay for research in every case, lost force on 20 April 2009 following the Constitutional Tribunal judgment K 20/07. Articles from before that date are still quoted online; the current rule is art. 31(1a).
Who pays
The rule is that the party carrying out the works pays (art. 31(1a)). The same applies to research ordered after a find during works: the conservator’s decision orders it at the cost of the person or organisation financing the works (art. 32(5)(3)).
Art. 82a provides a state subsidy from the minister responsible for culture when the planned research and its documentation cost more than 2% of the cost of the planned works. The subsidy equals the difference between the two (art. 82a(4)). It also applies to an unexpected discovery of a previously unknown archaeological monument during the works (art. 82a(2)). It does not apply when one of the parties is a public finance sector unit, or when the works are funded from the EU, the EEA Financial Mechanism or the Norwegian Financial Mechanism (art. 82a(3)). The subsidy is settled after the works and must be repaid if the 2% threshold is not in fact exceeded (art. 82a(5)–(6)).
Forms of protection: register, records, local plan
Art. 7 lists the forms of monument protection: entry in the register of monuments, entry on the Heritage Treasures List, recognition as a historic monument (pomnik historii), a cultural park, and protection provisions in a local zoning plan or in a location or zoning decision. The register is kept by the voivodeship conservator, in separate books for immovable, movable and archaeological monuments (art. 8).
Records (ewidencja) are a separate matter. They are not a form of protection under art. 7, but they matter in practice. The voivodeship conservator keeps voivodeship records, and the head of the municipality (wójt, burmistrz, prezydent miasta) keeps the municipal records of immovable monuments (art. 22(2) and (4)). Local plans must take into account monuments covered by the forms of protection and those in the voivodeship or municipal records (art. 19(1)); a local plan may set conservation protection zones (art. 19(3)); and draft local plans are agreed with the voivodeship conservator (art. 20).
The Construction Law (Prawo budowlane) adds the building-permit side. Works at a building or in an area entered in the register need the conservator’s permit, or a notification the conservator has not objected to, before the building permit or notification (art. 39(1)). For buildings and areas in the municipal records but not in the register, the building permit is issued in agreement with the voivodeship conservator (art. 39(3)).
Monuments in the environmental impact report
For projects that need an environmental impact assessment, the EIA Act (ustawa o udostępnianiu informacji o środowisku … oraz o ocenach oddziaływania na środowisko) brings heritage in directly. The assessment examines the direct and indirect effect of the project on, among other things, material assets, monuments and the landscape, including the cultural landscape (art. 62(1)(1)(b)–(ca)).
- The report must describe the monuments protected under the monuments act that lie near or within the direct range of the project’s impact (art. 66(1)(3)).
- It must compare the variants’ effects on monuments and the cultural landscape covered by existing documentation, in particular the register or records of monuments (art. 66(1)(6a)(d)).
- For roads that always require an assessment, it must also set assumptions for rescue research on identified monuments discovered during construction, a programme to protect existing monuments, and an analysis of risks to protected monuments, in particular archaeological ones (art. 66(1)(10)).
- The decision on environmental conditions sets the key conditions for using the environment, with particular regard to protecting monuments (art. 82(1)(1)(b)).
The wording matters: the report is built on monuments that are protected and documented. A site no one has recorded will not appear in it unless the desk-based search finds it.
When something turns up during works
Under art. 32(1), anyone who, during building works or earthworks, uncovers an object that may be a monument must stop any works that could damage it, secure the object and the place, and notify the voivodeship conservator without delay (or, if that is not possible, the head of the municipality). The conservator must inspect the find within 5 days of the notification; if not, the works may continue (art. 32(3)–(4)). After the inspection the conservator may allow the works to continue or order them to stay stopped while archaeological research is carried out at the cost of whoever finances the works (art. 32(5)). The stoppage may not exceed one month from delivery of that decision, extendable to six months for a monument of exceptional value (art. 32(6)–(7)).
Failing to notify and secure a chance archaeological find is a petty offence punishable by a fine (art. 116). Destroying or damaging a monument is a criminal offence (art. 108). This is why a late find on site costs more than one found at the desk.
Sources for a desk-based search
| Source | What it gives | What to keep in mind |
|---|---|---|
| NID geoportal and zabytek.pl | Registered immovable and archaeological monuments on a map, the AZP grid, WMS/WFS services | NID says the data is illustrative, cannot be the sole basis for administrative acts and that decisions should be checked with the conservator (NID) |
| Register of archaeological monuments (book C) | List of entries as open data (dane.gov.pl) | Only what has been entered by decision |
| Voivodeship conservator’s office (WUOZ) | Register decisions, voivodeship records, AZP site cards (KEZA), earlier research reports | The authoritative source; access rules vary by office |
| Municipal records and local plan | Monuments in the municipal records, conservation protection zones | Ask the municipality; check the status of the plan |
| AZP (Archaeological Record of Poland) | Sites recorded mainly by surface survey on standard sheets | Reflects what was visible on the surface when the area was walked |
| Archives, old maps, aerial photographs | Lost features, historic land use | Needs interpretation |
| LiDAR from Geoportal | Bare-earth relief, also under forest | Shows shapes, not dates or functions; every feature needs verification |
Why the register is not enough
The register of archaeological monuments lists 7,843 entries in NID’s open data as of 30 September 2026 (dane.gov.pl). NID reports about 500,000 sites in the national archaeological records (NID, 2019). Most known sites are therefore recorded but not registered, and art. 31(1a)(2) refers to land where archaeological monuments are located, not only to registered ones.
The records are also incomplete. NID’s standards for non-invasive archaeological research note that the best preserved, undisturbed sites often show on the surface only through a few finds (Standards, part 1). Surface survey works best on ploughed fields, where finds come to the surface; woodland is much harder to survey this way. The same standards treat the analysis of airborne laser scanning (ALS) data as a non-invasive method, require it before fieldwork in surface surveys and state that the national ALS data from the ISOK project can be considered sufficient for archaeological purposes. They also require every potential site picked from ALS data to be verified in the field where the land is accessible.
What to check at each stage
| Project stage | What to check | Sources |
|---|---|---|
| Site selection, land due diligence | Registered monuments, records, protection zones and known sites on or near the plot; signs of unrecorded features | NID geoportal, local plan, municipal records, WUOZ, LiDAR screening |
| Environmental impact report | Description of protected monuments near the project; comparison of variants (art. 66(1)(3) and (6a)(d)) | Register and records, WUOZ search, AZP, LiDAR as a supporting source |
| Design and building permit | Conservator’s permit or agreement (Construction Law art. 39); decision on the scope of research (art. 31(2)) | Voivodeship conservator |
| Before earthworks | Permit for archaeological research (art. 36(1)(5)); qualified research leader (art. 37e) | Archaeological contractor, voivodeship conservator |
| During works | Procedure for finds (art. 32) | Site manager, voivodeship conservator |
Adding LiDAR screening to the desk stage
A terrain model derived from airborne laser scanning removes vegetation and buildings and leaves the shape of the ground. Ramparts, ditches, barrows, terraces and old field systems that are hard to see on site often stand out in a hillshade. At the desk stage this has three uses: it adds candidates the register and records do not have, it shows the extent of known sites more precisely than an approximate point on a map, and it lets the field team plan where to walk first.
- Download every LiDAR sheet that covers the project area plus a buffer (NID’s standards suggest at least 100 m). The sheet finder lists them; where the data comes from explains the formats.
- Build a ground-only terrain model and light it from several sun directions. A single direction hides features that run parallel to the light. Reading LiDAR for archaeology shows what earthworks look like.
- Mark every candidate with coordinates and a short description, and set them against the register, records and AZP.
- Hand the candidates to an archaeologist for verification: field survey, and the conservator where a candidate falls within the works.
TerraTrace does steps 1 and 2 for a chosen area and part of step 3. It fetches the sheets from Geoportal, builds a 0.5 m ground model, renders hillshades from five azimuths and runs a detector trained on Polish earthworks. The result is a list of candidates with coordinates in EPSG:2180 (PUWG 1992) and a confidence score, which the team reviews on screen. The export is a QGIS package with the hillshade mosaics, the terrain model and the candidates as GeoJSON, ready to be used in an annex to a report.
Fig. 1TerraTrace · data source: GUGiK

For an archaeological firm, the practical gain is in the order of work: the search for a corridor or a large plot starts with a list of places to check, not with a blank map. For a developer or an environmental consultant, it is an earlier look at what may later surface in a conservator’s decision. You can see real results on TerraTrace in action and the evidence page.